A project is 60% complete. BAC = $500,000, AC = $350,000. The project manager calculates EV. What is the Schedule Performance Index (SPI)?

Project Management (PMP) Hard

Project Management (PMP) — Hard

A project is 60% complete. BAC = $500,000, AC = $350,000. The project manager calculates EV. What is the Schedule Performance Index (SPI)?

Key points

  • EV calculation directly impacts SPI
  • Percentage complete is crucial for EV
  • AC and EV comparison determines SPI
  • SPI value indicates schedule performance