In a project audit, auditors find that change requests were approved and implemented without updating the project baselines. This is a violation of which process?

Project Management (PMP) Hard

Project Management (PMP) — Hard

In a project audit, auditors find that change requests were approved and implemented without updating the project baselines. This is a violation of which process?

Key points

  • Change requests must be formally approved and documented
  • Project baselines should reflect approved changes
  • Integrated Change Control governs the change management process
  • Updating baselines is crucial for project control