A Scrum team has been averaging 40 story points per sprint. During release planning, they need to deliver 200 story points of features. Assuming 5% velocity degradation after each sprint due to technical debt, which is the BEST estimate for number of sprints needed?

Project Management (PMP) Hard

Project Management (PMP) — Hard

A Scrum team has been averaging 40 story points per sprint. During release planning, they need to deliver 200 story points of features. Assuming 5% velocity degradation after each sprint due to technical debt, which is the BEST estimate for number of sprints needed?

Key points

  • Velocity degradation impacts sprint duration
  • Release planning requires accurate velocity estimates
  • Technical debt affects team velocity
  • Story points measure feature complexity