A project has EV = $80,000, AC = $100,000, and BAC = $200,000. What is the Estimate at Completion (EAC) assuming current CPI continues?

Project Management (PMP) Hard

Project Management (PMP) — Hard

A project has EV = $80,000, AC = $100,000, and BAC = $200,000. What is the Estimate at Completion (EAC) assuming current CPI continues?

Key points

  • CPI is crucial for EAC calculation
  • Incorrect CPI leads to wrong EAC
  • BAC and EV are used to find the remaining work
  • Formula application is key