A project manager is calculating the To-Complete Performance Index (TCPI) based on BAC. The project has BAC = $500,000, EV = $200,000, and AC = $250,000. What is the TCPI?

Project Management (PMP) Hard

Project Management (PMP) — Hard

A project manager is calculating the To-Complete Performance Index (TCPI) based on BAC. The project has BAC = $500,000, EV = $200,000, and AC = $250,000. What is the TCPI?

Key points

  • TCPI measures the required performance to complete the project
  • BAC and EV are crucial in determining the remaining work
  • AC influences the efficiency needed for completion
  • The formula's numerator and denominator directly impact the TCPI value