A project manager is reviewing a cost performance report showing SPI = 1.10 and CPI = 0.92. What is the most likely interpretation?

Project Management (PMP) Medium

Project Management (PMP) — Medium

A project manager is reviewing a cost performance report showing SPI = 1.10 and CPI = 0.92. What is the most likely interpretation?

Key points

  • SPI above 1 indicates schedule advancement
  • CPI below 1 signals cost overruns
  • Combined metrics reveal performance nuances
  • Schedule and cost metrics must be considered together

Ready to go further?

Related questions