A project manager is analyzing activity sequences and finds that Activity B cannot start until Activity A is 50% complete. This represents which type of dependency?

Project Management (PMP) Medium

Project Management (PMP) — Medium

A project manager is analyzing activity sequences and finds that Activity B cannot start until Activity A is 50% complete. This represents which type of dependency?

Key points

  • Start-to-Start dependencies involve concurrent progress
  • Lag represents a delay or offset in activity start
  • Dependency type affects project schedule and timeline
  • Understanding activity relationships is crucial for sequencing