During a project, a contractor files a claim stating the buyer issued a constructive change that increased the contract scope without formal authorization. The most appropriate first step for the project manager is to:

Project Management (PMP) Hard

Project Management (PMP) — Hard

During a project, a contractor files a claim stating the buyer issued a constructive change that increased the contract scope without formal authorization. The most appropriate first step for the project manager is to:

Key points

  • Verify contract terms to identify potential breaches
  • Documenting events helps establish a factual record
  • Constructive changes can be implicit or explicit
  • Contract terms govern the resolution process
  • Factual records support negotiations