The Cost Performance Index (CPI) for a project is 0.85. This means the project is:

Project Management (PMP) Medium

Project Management (PMP) — Medium

The Cost Performance Index (CPI) for a project is 0.85. This means the project is:

Key points

  • A CPI below 1 signifies cost overruns
  • Earned value is less than actual cost when CPI is 0.85
  • Schedule performance is not directly indicated by CPI
  • Budget variance is the primary concern here