A project that has been executing for 6 months has accumulated actual costs of $900,000 against a plan of $800,000, with earned value of $750,000. The project manager forecasts using the EAC = AC + (BAC – EV) / CPI formula. If BAC = $2,000,000, what is the EAC approximately?

Project Management (PMP) Hard

Project Management (PMP) — Hard

A project that has been executing for 6 months has accumulated actual costs of $900,000 against a plan of $800,000, with earned value of $750,000. The project manager forecasts using the EAC = AC + (BAC – EV) / CPI formula. If BAC = $2,000,000, what is the EAC approximately?

Key points

  • The EAC formula requires accurate AC, EV, and BAC values.
  • CPI is crucial in determining the EAC, as it reflects cost efficiency.
  • Incorrect BAC or EV values can significantly impact the EAC calculation.

Ready to go further?

Related questions