A project is in trouble: CPI = 0.75 and SPI = 0.80. The project manager must present a recovery plan. Which action addresses BOTH performance issues simultaneously?

Project Management (PMP) Hard

Project Management (PMP) — Hard

A project is in trouble: CPI = 0.75 and SPI = 0.80. The project manager must present a recovery plan. Which action addresses BOTH performance issues simultaneously?

Key points

  • Identifies the dual performance issues of CPI and SPI
  • Addresses cost and schedule overruns simultaneously
  • Involves optimizing resource utilization for better performance
  • Eliminates non-critical rework to improve efficiency