Which schedule compression technique adds resources to critical path activities to shorten the schedule, often increasing cost?

Project Management (PMP) Medium

Project Management (PMP) — Medium

Which schedule compression technique adds resources to critical path activities to shorten the schedule, often increasing cost?

Key points

  • Crashing accelerates critical tasks by adding resources
  • Fast tracking involves performing tasks in parallel
  • Resource leveling aims to balance resource allocation
  • Schedule baseline update is not a compression technique